ResourcesProtections · Engineering

Solar farm protections: what each one watches

July 202612 min read

A protection scheme reads badly when you look at it as a list of devices. It is three different things, and they are worth keeping apart: the function is what decides, the apparatus is what interrupts, and the element is what gets protected. This guide separates the three, explains the two questions that cause the most confusion — the distance relay and arc flash — and marks where your scheme ends and the transmission operator's begins.

What a distance relay is (21)

A distance relay protects a line, not a point. It does not watch current: it measures V/I and obtains an impedance, which is proportional to the distance to the fault. That is why it is drawn on an R-X plane and not on a time-current curve, and why it does not share a screen with a 50/51.

The three zones of a 21, and why they exist
ZoneTypical settingTimeWhat for
Z180% of the lineInstantaneousTrips right away. It stops short on purpose: it must never see past the remote bus.
Z2120%~0.3 sCovers the 20% that Z1 does not see, and reaches into the next line. It waits, to give the relay over there its turn.
Z3180%~1 sRemote backup: if the next line's relay fails to clear, this one does.

Your protections and the grid's: three different questions

Inside the plant, selectivity is achieved with time. Fuse, inverter, string box, feeder, incomer: every series pair has to be separated by the CTI, on the order of 0.2 to 0.3 seconds. The one below clears first and the one above waits. That is the entire content of a coordination table.

Looking outward, the question changes: a fault in your medium voltage has to be opened by your incomer before the transmission operator's relay at the point of connection decides the problem is theirs. If your step is slower than their step, they take out the whole line, and your fault becomes an outage for everyone on it.

And from the outside comes the one that gets forgotten most: a fault in the grid sinks the voltage at your point of connection, and your interface protections — 27 undervoltage, 59 overvoltage — will see that sag. If you trip, you disconnected the plant over somebody else's problem, and the grid code obliges you to ride it out. That is the ride-through envelope, and it is the reason the 27/59 settings are not chosen by looking at the plant alone.

What the transmission operator asks of you: infeed

Your plant injects current at the point of connection. For a fault further down the line, that injection changes what the grid's distance relay measures: the contribution entering between the relay and the fault makes it read more impedance than is really there, and its zone shortens. That is the under-reach effect, and it means their zone 2 stops covering what it covered before you existed. The interconnection study asks for exactly that number: how far each zone moved with the plant connected and without it.

What arc flash is, and why the calculation sometimes refuses to run

If an arc strikes inside a switchgear cubicle while somebody is working there, the question is not how much current flows: it is how much energy the person receives, in cal/cm². That defines the personal protective equipment and the approach boundary. The calculation consumes the bolted-fault current, the clearing time — that is, your own protection settings —, the conductor gap, the electrode configuration and the enclosure size. That is why arc flash runs after coordination and never before: if you change the coordination, the incident energy changes.

There are two legitimate reasons a bus may be left declared as not calculated:

  • It is outside the range of the standard. The IEEE 1584-2018 model is empirical, fitted with tests between 208 V and 15 kV. A 33 kV bus falls outside, and the correct move is to refuse rather than extrapolate: a regression evaluated outside its range, printed in a report, is an invented number. For higher voltages, use the Lee method or the transmission operator's practice.
  • A datum is missing that nobody can assume for you. The electrode configuration — VCB, VCBB, HCB, VOA, HOA — and the equipment class change the result substantially. Without that explicit choice, the result is not ratified and should not be printed.

The functions: the ANSI vocabulary

The functions are named by ANSI/IEEE C37.2 with a number, and that number is the vocabulary you use to talk to the transmission operator. The function lives in the relay; what interrupts is the breaker. A flawless 87T is worthless if the breaker does not open, and that is why 50BF and 74TCS exist.

Overcurrent and directionals
ANSIWhat it does
50Instantaneous phase overcurrent. Above the threshold, it trips without waiting. For the bolted fault close to the relay.
51Time-delayed phase overcurrent, IEC 60255 inverse curve: more current, less time. It is the one graded with the CTI.
50N / 51NThe same, but on the residual current: the sum of the three phases differing from zero indicates a ground fault. A much lower threshold, because a ground fault can be a few amperes and still kill.
49Thermal image. It does not watch the peak, it watches accumulated heat. For transformers and cables, which withstand overload for a while and not a while longer.
67 / 67NOvercurrent with direction. Indispensable when current can come from both sides: a medium-voltage ring, or a plant that injects. Without 67, in a ring the wrong breaker opens and the healthy half is lost too.
Differentials and distance: selectivity without waiting for anyone
ANSIWhat it does
87TTransformer: compares what goes in with what comes out. If it does not balance, the fault is inside. Instantaneous and coordinated with nobody, because its zone is its own current transformers.
87BThe same over a bus.
87LThe same over a line, with a communications channel between the two ends.
64 REFRestricted earth fault: catches ground faults near the transformer neutral, exactly where the 87T loses sensitivity.
21Distance: measures impedance, which is distance. For long lines, where the 51 no longer discriminates between here and there.
Grid interface: the ones the code fixes
ANSIWhat it does
27 / 59Undervoltage and overvoltage.
81U / 81OUnderfrequency and overfrequency.
81RRate of change of frequency (df/dt): detects that the plant was left in an island.
Anti-islandingThe combined function: do not keep feeding a section the grid has already let go.
Transformer, switching and supervision
ANSIWhat it does
24Overexcitation (V/Hz): high voltage or low frequency saturates the core.
63Buchholz: a mechanical gas and pressure relay. An internal arc generates gas before it becomes measurable current. It is the one that saves the transformer.
25Synchronism check before closing: that the two ends are in phase.
79Automatic reclosing. Most overhead-line faults are fleeting.
50BFBreaker failure: a trip was ordered and current keeps flowing, so trip the ones upstream.
60FLVoltage transformer supervision. If the voltage signal is lost, a 21 or a 67 starts lying: block them, do not let them opine.
60CTSThe same over the current transformer.
74TCSTrip circuit supervision: verifies the wire to the trip coil is healthy. A trip that does not arrive is having no protection, and without this function nobody finds out until the day of the fault.

The apparatus: what actually interrupts

Switchgear by voltage level
LevelApparatus
DCString fuse · load-break switch · surge arrester · insulation monitor
Low voltageMoulded-case breaker · air circuit breaker · fuse · surge arrester · residual-current device
Medium voltageCircuit breaker · load-break switch · disconnector · earthing switch · fuse · surge arrester · recloser · ring main unit · neutral earthing resistor · zig-zag earthing transformer
High voltageCircuit breaker · disconnector · earthing switch · surge arrester
MeasurementProtection relay · current transformer · voltage transformer · billing meter · power-quality meter

The last two in medium voltage interrupt nothing: the neutral resistor and the zig-zag define how the system is earthed, which is what decides how much ground-fault current exists — and therefore whether the 51N can see it. It is a project decision taken before a single relay is chosen.

And the third concept, the one you count when you talk about coverage: the protectable elements.

  • DC string · combiner box · inverter AC output · low-voltage bus.
  • Medium-voltage block transformer · medium-voltage feeder · medium-voltage collector bus.
  • Step-up transformer · high-voltage bus · high-voltage line to the point of connection.

The typical scheme, level by level

What each point of a PV plant carries
WhereWhat it carries
StringFuse, only if there are three or more strings in parallel (IEC 62548)
DC sideInsulation monitor and arc-fault detection
Inverter AC outputMoulded-case or air circuit breaker
MV block transformer50/51 + 50N/51N · 63 · 87T if it is large
MV feeder50/51 + 50N/51N · 67 if it is a ring
MV collector bus87B · 50BF
Step-up transformer87T · 64REF · 63 · 49 · 24
HV bus and line21 · 87L · 79 · 25 · 50BF · 60FL
Point of connection27/59 · 81U/81O/81R · anti-islanding

The last row is the only one negotiated with the transmission operator: those are the settings that go into the protection coordination settlement. Everything above it belongs to the project, and its engineering defines it.

Standards cited

  • IEEE C37.2Device and function identification numbers. It is the origin of the 21 / 50 / 51 / 87 vocabulary any scheme is written in.
  • IEC 60255-151Inverse-time characteristics of overcurrent functions: normal, very and extremely inverse families, and the time multiplier.
  • IEEE 1584-2018Arc-flash incident energy calculation. An empirical model valid between 208 V and 15 kV: outside that range the standard does not apply, and extrapolating it is not conservative.
  • IEC 62548Design requirements for photovoltaic arrays, including the string-protection rule when there are three or more parallel branches.
  • IEC 60909Short-circuit current calculation, the basis of the duty with which switchgear is specified.
  • IEEE 80Safety in AC substation grounding: grid resistance, ground potential rise and step and touch voltages.
  • Procedimiento Técnico N°4, Annex I (3 October 2023 version)Argentina's interconnection requirements for wind and photovoltaic generation, including the voltage-sag ride-through envelope against which the 27/59 settings are judged.

Informational content current as of July 2026. It is not legal or regulatory advice: always verify against the standard in force and the requirements of your grid operator.

Every function on this list has a study behind it

ELAP builds the scheme from the plant model, grades the series pairs against the CTI and runs the distance-relay zone sweep with the operator's grid behind it — declaring in each case what is owned scope and what is screening.

Request a demoView documentation