Mendoza · LavalleConstruction

PSF Lavalle Solar

5.0 MWp · Single-axis tracker · bifacial · 10-year MATER PPA · USD 58/MWh

Back to explore

Key factskey information sheet · all figures are examples

ItemValueSource
What it is5.01 MWp (4.2 MWac) solar plant in Lavalle, Mendoza · Single-axis tracker · bifacial · sells its energy under 10-year MATER PPA at USD 58/MWhELAP estimate ELAP · report rev C · P50/P90 study · 05/15/2026
Amount being raisedUSD 1.70 M from the crowd, out of a CAPEX of USD 3.06 M (USD 0.611/Wp) · 100 % raised · closed 06/2026Actual 36 % · Contract 64 % as of 08/12/2026
Minimum ticketTo be defined: financing has not openedContract Platform terms, art. 9 · 07/01/2026
ReturnP50 11.2 % · P90 9.9 % of contributed capital in year 1 · projected, not guaranteedELAP estimate ELAP · trust model, report rev C · 05/15/2026
Term10-year PPA · 25-year useful lifeContract Signed MATER PPA · 03/20/2026
Main risksConstruction · Price after the PPAELAP estimate ELAP · report rev C · P50/P90 study · 05/15/2026
Total feesUSD 359,757 one-off (11.8 % of CAPEX) · USD 180,644 per year (29.9 % of year-1 revenue, including debt interest)Contract Trust agreement, annex III · 06/15/2026

[Model: key information sheet under EU Regulation 2020/1503 and CNV RG 717/2018 · to be checked in the legal memo]

TablesMV stationGrid lineSite boundary
Plant — Plan
166 1P tables of 2 × 261 MV station of 5 MVA · 13.2 kV13.2 kV MV line · 1.8 km11 ha used of 30ELAP layout, report revision

Who takes part

RoleWhoContributionStatus
LandLocal farmer (example)In-kind contribution for equityReady
InvertersElectro Cuyo (example)Awarded · 50 % contributed for equityReady
EPCConstructora Jarilla (example)Turnkey · under constructionReady
BuyerWinery, Luján de Cuyo10-year PPA · USD 58/MWhReady
TrusteeFiduciaria Pampa S.A. (example)Ready
EngineeringELAPrev C, as builtReady

Capital structure example

Land, in kind · USD 0.10 M · 3 %Equipment, in kind · USD 0.07 M · 2 %Crowd · USD 1.70 M · 56 %Bank debt · USD 1.18 M · 39 %

Total USD 3.06 M = CAPEX, sum of the bill of quantities · USD 0.611/Wp · contributed capital (excluding debt) USD 1.87 M

P50P90
Annual distribution — % of paid-in capital
0 %5 %10 %15 %20 %debt repaidPPA endsP50 10.8 %P90 9.6 %1510152025year
Years 1 to 10 with debtRises once the debt is repaidDrops when the PPA ends (spot USD 45/MWh, example)Projected, not guaranteed

Explicit risks

RiskWhat can happenWhat limits it
ConstructionDelay of the MV station transformer: 6 weeks.The EPC absorbs the penalty under the contract.
Price after the PPAThe PPA covers 10 years; after that, spot.Base scenario USD 45/MWh.

Questions

No questions yet.

Financing

Closed. The plant is in Construction.

Grid access

Node
Lavalle 66/13.2 kV substation
Free capacity
8 MW (CAMMESA, public data)
Requested capacity
4.2 MW
Dispatch priority
Assigned 02/2026
Guarantee deposit
Posted

Energy buyer

Winery, Luján de Cuyo · MATER Large User

10-year MATER PPA · USD 58/MWh

Stages

Land09/2025
Engineering12/2025
Grid access02/2026
Financingclosed 06/2026
todayConstruction45 % complete
Operation03/2027

01Equipment and quantities24 lines · total USD 3,057,800 = CAPEX

CategoryDescriptionManufacturer and modelSpecificationQuantityUnit priceTotalSourcePurchase status
Main equipment, item by item · click a row to see warranty, country and datasheet
Minor items, by category
Bill of quantities total · 0.611 USD/Wp over 5.007 MWpUSD 3,057,800

Prices in USD excluding VAT. Supplier, EPC, O&M and trustee names are examples; manufacturers and models are real and their prices are examples.

02Prices and CAPEXUSD 3,057,800 · 0.611 USD/Wp

CategoryUSDUSD/Wp% of totalMarket reference USD/WpPlatform average USD/WpSource
EquipmentUSD 709,4850.14223.2 %0.1550.143Actual 79 % · Contract 21 % as of 08/12/2026
StructureUSD 638,4360.12820.9 %0.1250.119Actual 71 % · Contract 29 % as of 07/30/2026
Electrical BOSUSD 393,0210.07912.9 %0.0800.076Actual 17 % · Contract 83 % as of 08/05/2026
Medium voltageUSD 173,2000.0355.7 %0.0350.047Contract as of 07/02/2026
Civil worksUSD 325,4260.06510.6 %0.0600.061Contract as of 07/01/2026
Grid connectionUSD 291,0000.0589.5 %0.0500.061Contract as of 07/01/2026
EngineeringUSD 60,0790.0122.0 %0.0120.012Contract as of 12/15/2025
DevelopmentUSD 202,6340.0406.6 %0.0350.038Actual 6 % · Contract 94 % as of 06/20/2026
TrusteeUSD 18,0000.0040.6 %0.0030.003Actual as of 06/20/2026
InsuranceUSD 11,3880.0020.4 %0.0020.002Contract as of 06/28/2026
Platform feeUSD 51,0000.0101.7 %0.0100.010Contract as of 07/01/2026
ContingencyUSD 101,2230.0203.3 %0.0200.020Contract as of 12/15/2025
Financing costUSD 45,8340.0091.5 %0.0120.010Contract as of 12/15/2025
TaxesUSD 37,0740.0071.2 %0.0080.008Contract as of 12/15/2025
TotalUSD 3,057,8000.611100 %0.6070.612Actual 36 % · Contract 64 % as of 08/12/2026

Market reference: ELAP estimate ELAP · 2026 market reference, 19 budget prices · 09/15/2026. The platform average is that of the other 6 projects on this page. Each category is the sum of its lines in the bill of quantities.

03Open tenderanonymous until awarded, named afterwards

Equipment · String inverter 250 kW, 1,500 VAwarded on 06/20/2026 · 17 pcs · 2 quotes
BidderOfferUnit priceTotalVersus lowestLead timeResult

Why it won: The second cheapest (1 % above B), but contributes 50 % of the order for equity and delivers in 10 weeks versus 16.

04Use of fundsUSD 1,424,984 disbursed of USD 2,883,425

SourcesUSD%
Land, in kindUSD 100,0003.3 %
Equipment, in kindUSD 74,3752.4 %
CrowdUSD 1,700,00055.6 %
Bank debtUSD 1,183,42538.7 %
TotalUSD 3,057,800100 %
UsesUSD%
EquipmentUSD 709,48523.2 %
StructureUSD 638,43620.9 %
Electrical BOSUSD 393,02112.9 %
Medium voltageUSD 173,2005.7 %
Civil worksUSD 325,42610.6 %
Grid connectionUSD 291,0009.5 %
EngineeringUSD 60,0792.0 %
DevelopmentUSD 202,6346.6 %
TrusteeUSD 18,0000.6 %
InsuranceUSD 11,3880.4 %
Platform feeUSD 51,0001.7 %
ContingencyUSD 101,2233.3 %
Financing costUSD 45,8341.5 %
TaxesUSD 37,0741.2 %
TotalUSD 3,057,800100 %

In-kind contributions (USD 174,375: land and equipment for equity) do not go through the account. The rest is paid from the trust account against certified milestones by the independent engineer, and every disbursement is published here.

DateMilestoneAmountUseCertificateStatus
06/20/2026Financing closeUSD 231,713Engineering, development, trustee and placement feeTrust closing recordPaid
08/20/2026EPC signing and advanceUSD 397,757EPC advanceCertificate no. 1 · Estudio Ingeniería Zonda (example)Paid
09/20/2026Modules delivered to siteUSD 795,514Modules and inverters on deliveryCertificate no. 2 · Estudio Ingeniería Zonda (example)Paid
10/20/2026Pile drivingUSD 318,205Pile driving and structureon certificationPlanned
11/20/2026Mechanical installationUSD 344,723Mechanical installationon certificationPlanned
12/20/2026Electrical installationUSD 318,205Electrical BOS and cableson certificationPlanned
01/20/2027MV station and lineUSD 265,171MV stations, line and outgoing bayon certificationPlanned
02/20/2027CAMMESA commercial operationUSD 212,137EPC balance, contingency and retentionon certificationPlanned
Total through the trust accountUSD 2,883,425CAPEX minus in-kind contributions

05Who gets paid whatUSD 359,757 one-off · USD 180,644 per year

PartyWhoItemBasisAmount USDWhenSource
PlatformMercado SolarPlacement fee3 % of the crowd raise, once at closeUSD 51,000OnceContract Platform terms, art. 9 · 07/01/2026
PlatformMercado SolarAdministration and secondary market1 % of revenue, per yearUSD 6,040Per yearContract Platform terms, art. 10 · 07/01/2026
ELAPELAPEngineering0.012 USD/WpUSD 60,079OnceContract Trust agreement, annex III · 06/15/2026
ELAPELAPDevelopment0.018 USD/WpUSD 90,118OnceContract Trust agreement, annex III · 06/15/2026
TrusteeFiduciaria Pampa S.A. (example)Trust formationfixed feeUSD 18,000OnceContract Trust agreement, annex III · 06/15/2026
TrusteeFiduciaria Pampa S.A. (example)Trust administration0.8 % of revenue, per yearUSD 4,832Per yearContract Trust agreement, annex III · 06/15/2026
EPCConstructora Jarilla (example)EPC's declared margin10 % of the works in its scope (included in the bill of quantities)USD 116,210OnceContract Trust agreement, annex III · 06/15/2026
O&MOperadora Solar Andes (example)Operation and maintenanceUSD 15,000 per MWp per yearUSD 75,098Per yearContract Trust agreement, annex III · 06/15/2026
BankBanco Regional (example)Debt structuring1 % of the debtUSD 11,834OnceContract Trust agreement, annex III · 06/15/2026
BankBanco Regional (example)Year-1 interest8 % a year on the debtUSD 94,674Per yearContract Trust agreement, annex III · 06/15/2026
Independent engineerEstudio Ingeniería Zonda (example)Technical review and construction certificationUSD 2,500 per MWpUSD 12,516OnceContract Trust agreement, annex III · 06/15/2026
One-off, within CAPEXUSD 359,75711.8 % of CAPEX
Annual, year 1USD 180,644from the payment waterfall
Declared conflict of interest. ELAP is at once engineer, developer and platform of this project: it charges for engineering, development and the platform fees. That is why the technical review is signed by an independent engineer (Estudio Ingeniería Zonda (example)), who also certifies every milestone before a disbursement.

06Production and assumptionsP50 10.41 GWh · P90 9.76 GWh per year · Source: ELAP estimate · ELAP · report rev C · P50/P90 study · 05/15/2026

Data or assumptionValue
P50 production10.41 GWh per year · 2,080 kWh/kWp
P90 production9.76 GWh per year · 1,950 kWh/kWp
Weather data sourcePVGIS-SARAH3 cross-checked with Solcast
Years in the series2005 to 2023 (19 years)
Global horizontal irradiation (GHI)1,985 kWh/m² per year
Bifacial gain7.2 %
Total system losses14.5 %
Soiling2.0 % with quarterly cleaning
Availability99.0 %
Grid curtailment2.0 %
Annual module degradation0.4 % per year (manufacturer's linear warranty)
Combined uncertainty (1 σ)4.9 % · P90 = P50 × (1 − 1.28 σ)
Download ELAP's P50/P90 studyPDF of report rev C, with the weather series and the loss breakdown.

07Revenue10-year MATER PPA

ItemValueSource
PriceUSD 58/MWhContract Signed MATER PPA · 03/20/2026
Term10 years from commercial operationContract Signed MATER PPA · 03/20/2026
Indexation1.5 % a year in USD from year 4Contract Signed MATER PPA · 03/20/2026
CounterpartyWinery, Luján de Cuyo · MATER Large UserContract Signed MATER PPA · 03/20/2026
GuaranteesBank guarantee for 2 months of billingContract Signed MATER PPA · 03/20/2026
Energy covered100 % of the energyContract Signed MATER PPA · 03/20/2026
After the contractSpot, USD 45/MWh as an exampleELAP estimate ELAP · report rev C · 05/15/2026

08Payment waterfallyear 1 · projected

OrderItemBasisUSD year 1, P50% of revenueUSD year 1, P90Source
Energy sales revenue10.41 GWh × USD 58/MWhUSD 603,991100.0 %USD 566,242Contract Signed MATER PPA · 03/20/2026
1Operation and maintenanceUSD 15,000 per MWp per year−USD 75,09812.4 %−USD 75,098Contract Trust agreement, annex III · 06/15/2026
2Operational all-risk insurance0.4 % of CAPEX per year−USD 10,7021.8 %−USD 10,702ELAP estimate ELAP · trust model, report rev C · 05/15/2026
3Trustee fee0.8 % of revenue−USD 4,8320.8 %−USD 4,530Contract Trust agreement, annex III · 06/15/2026
4Platform administration fee1 % of revenue−USD 6,0401.0 %−USD 5,662Contract Platform terms, art. 10 · 07/01/2026
5Municipal fees and gross receipts tax1.2 % of revenue−USD 7,2481.2 %−USD 6,795ELAP estimate ELAP · trust model, report rev C · 05/15/2026
6Income tax35 % of profit, with 25-year depreciation−USD 99,08016.4 %−USD 86,264ELAP estimate ELAP · trust model, report rev C · 05/15/2026
7Debt service (principal and interest)USD 1.18 M at 8 % over 10 years−USD 176,36529.2 %−USD 176,365Contract Trust agreement, annex III · 06/15/2026
8Inverter replacement reserveUSD 3,000 per MWp per year−USD 15,0202.5 %−USD 15,020ELAP estimate ELAP · trust model, report rev C · 05/15/2026
9Distribution to investors11.2 % of contributed capitalUSD 209,60634.7 %USD 185,805ELAP estimate ELAP · trust model, report rev C · 05/15/2026

First operation, taxes and debt; then reserves; and only after that the investors. The return on the sheet is the last line divided by the contributed capital (USD 1,874,375).

09Sensitivityyear 1 · same model as the payment waterfall · Source: ELAP estimate · ELAP · trust model, report rev C · 05/15/2026

CaseYear-1 returnVersus baseDistribution USDPer USD 1,000
Base case (P50)11.2 %—USD 209,606USD 112
Sale price −10 %9.2 %−2.0 ppUSD 171,525USD 92
P90 production9.9 %−1.3 ppUSD 185,805USD 99
CAPEX +10 %, with more debt9.4 %−1.8 ppUSD 176,183USD 94
20 % exchange-rate gap9.3 %−1.9 ppUSD 174,672USD 93

CAPEX +10 %: the overrun is financed with more debt. Exchange-rate gap: revenue is collected in pesos at the official rate and the investor converts to dollars at a rate 20 % higher.

10Construction progress20 % actual versus 26 % planned · Source: Actual · Progress certificates · Estudio Ingeniería Zonda (example) · 10/10/2026

MilestonePlannedActualDelay
EPC signing and advance07/15/202607/15/2026on time
Modules delivered to site09/15/202609/24/20269 days
Pile driving10/15/202610/29/202614 days
Mechanical installation11/15/202612/06/202621 days
Electrical installation12/15/2026pending—
MV station and line01/15/2027pending—
Energization02/15/2027pending—
CAMMESA commercial operation03/15/2027pending—
Main equipmentOf 8
Awarded or later8
Purchased8
Delivered to site6
Installed3
MonthPlannedActualCurve
07/20260 %0 %
08/20263 %1 %
09/202613 %8 %
10/202626 %20 %
11/202642 %—
12/202658 %—
01/202774 %—
02/202787 %—
03/202797 %—
04/2027100 %—

Purchase status of each item in section 1. Actual dates and progress: independent engineer's certificates.

11Change logpublic to everyone

DateWhat changedFromToWhySource
05/15/2026ELAP reportrev Brev CDetailed engineering closed with the awarded equipment.ELAP estimate ELAP · report rev C · 05/15/2026
08/12/2026Modules: sourceContract · USD 0.112/WpActual · USD 0.112/WpInvoice paid and modules on site.Actual Invoice A-0004-00002231 · 08/12/2026
09/02/2026Planned energization01/15/202702/05/20276-week transformer delay; the EPC absorbs the penalty.Contract EPC note no. 7 · 09/02/2026

When a figure changes source (estimated, quoted, contracted, actual), the previous one stays here.

12Documentsdata room

  • Trust agreementPDF · 06/2026Registered users only
  • ProspectusPDF · 04/2026View
  • Power purchase agreementPDF · 03/2026Registered users only
  • ELAP engineering report, rev CPDF · 05/2026View
  • Grid access studyPDF · 02/2026View
  • Independent engineer's technical auditPDF · 10/2026 · progress certificate 3Registered users only
  • Quarterly financial statements of the trustPDF · 09/2026 · Q3 2026Registered users only