San Luis · Quines, Ayacucho departmentFinancing

PSF Quines I

12.0 MWp · Single-axis tracker · bifacial · 15-year MATER PPA · USD 57/MWh

Back to explore

Key factskey information sheet · all figures are examples

ItemValueSource
What it is12.02 MWp (10.0 MWac) solar plant in Quines, Ayacucho department, San Luis · Single-axis tracker · bifacial · sells its energy under 15-year MATER PPA at USD 57/MWhELAP estimate ELAP · report rev B · P50/P90 study · 09/15/2026
Amount being raisedUSD 3.80 M from the crowd, out of a CAPEX of USD 7.35 M (USD 0.612/Wp) · 64 % raised · closes 12/15/2026Contract 76 % · Quote 7 % · ELAP estimate 17 % as of 10/10/2026
Minimum ticketUSD 500 · 5 shares of USD 100, upfront or in installmentsContract Platform terms, art. 9 · 07/01/2026
ReturnP50 11.3 % · P90 9.9 % of contributed capital in year 1 · projected, not guaranteedELAP estimate ELAP · trust model, report rev B · 09/15/2026
Term15-year PPA · 25-year useful lifeContract Signed MATER PPA · 08/28/2026
Main risksCurtailment · Price · Exchange rateELAP estimate ELAP · report rev B · P50/P90 study · 09/15/2026
Total feesUSD 822,691 one-off (11.2 % of CAPEX) · USD 357,896 per year (25.1 % of year-1 revenue, including debt interest)Contract Trust agreement, annex III · 10/10/2026

[Model: key information sheet under EU Regulation 2020/1503 and CNV RG 717/2018 · to be checked in the legal memo]

TablesMV stationGrid lineSite boundary
Plant — Plan
424 1P tables of 2 × 262 MV stations of 5 MVA · 33 kV33 kV MV line · 6.5 km to San Francisco substation28 ha used of 85ELAP layout, report revision

Who takes part

RoleWhoContributionStatus
LandEst. La Esperanza, García estateIn-kind contribution for equity · 85 haReady
ModulesImportadora Andina (example)Awarded · sale in 18 trust installmentsReady
TrackersTrackers del Oeste (example)Awarded · in-kind contribution for equityReady
Inverters2 quotesOpen tender · closes 10/30/2026In progress
EPCConstructora Huarpe (example)Turnkey · fixed price · 2-year warrantyReady
O&MOperadora Solar Andes (example)5 years, renewableReady
BuyerFood manufacturer, Villa Mercedes15-year MATER PPA · USD 57/MWh · 85 % of the energyReady
TrusteeFiduciaria Pampa S.A. (example)Contract signed 10/2026Ready
Independent engineerEstudio Ingeniería Zonda (example)Design review and construction certificationReady
InsurerAseguradora Ruta (example)All-risk construction and operation · being quotedIn progress
BankBanco Regional (example)8 % · 10 years · letter of intentIn progress
EngineeringELAPLayout, P50/P90, single-line diagram, bill of quantities and costs · rev BReady

Capital structure example

Land, in kind · USD 0.30 M · 4 %Equipment, in kind · USD 1.13 M · 15 %Crowd · USD 3.80 M · 52 %Bank debt · USD 2.13 M · 29 %

Total USD 7.35 M = CAPEX, sum of the bill of quantities · USD 0.612/Wp · contributed capital (excluding debt) USD 5.23 M

P50P90
Annual distribution — % of paid-in capital
0 %5 %10 %15 %20 %debt repaidPPA endsP50 10.9 %P90 9.6 %1510152025year
Years 1 to 10 with debtRises once the debt is repaidDrops when the PPA ends (spot USD 45/MWh, example)Projected, not guaranteed

Explicit risks

RiskWhat can happenWhat limits it
CurtailmentIf the grid becomes congested, CAMMESA curtails injection and less energy is sold.Dispatch priority assigned; free node capacity of 18 MW for 10 MW requested; the P90 already deducts 3 %.
PriceThe PPA covers 15 years; after that the energy is sold at market price, which is lower and uncertain.The chart shows the drop from year 16 with an example price of USD 45/MWh.
Exchange rateThe PPA is in USD and collected in pesos at the official exchange rate; distributions follow that exchange rate.Adjustment clause; the exchange-rate gap is a risk borne by the investor (see sensitivity).
BuyerIf the buyer does not pay or shuts down, the plant sells on the spot market at a lower price.Guarantee of 3 months of billing; rated buyer; the remaining 15 % already goes to the spot market.
Construction and scheduleCost overruns or delays push back the start of distributions.Turnkey EPC with a fixed price and warranty; an independent engineer certifies progress.
Priority that never reaches operationMany projects with assigned dispatch priority never reach operation: the priority expires and the deposit is lost.Financing with a fixed close; if the minimum is not reached, the paid-in amounts are refunded.

Questions

  • What happens if the plant produces less than the P90? · machine translationThe P90 is the scenario exceeded 9 years out of 10. There may be worse years: that year's distribution falls proportionally. There is no guaranteed return. · machine translationProject team · 10/02/2026
  • Am I paid in dollars? · machine translationDistributions are calculated in USD and paid in pesos at the official exchange rate on the payment date, unless you have an enabled USD account. · machine translationFiduciaria Pampa · 10/05/2026
  • Can I sell before the 25 years are up? · machine translationYes, on the platform's secondary market once the plant is in operation. The price is set by supply and demand. · machine translationProject team · 10/08/2026

Financing closes 12/15/2026

64 % · USD 2.43 M of USD 3.80 M · 80 % minimum to close
Minimum ticketUSD 5005 shares · or 12 installments of USD 44 · or 18 of USD 30
Return
9.9 to 11.3 % in year 1 (P90 to P50), projected, not guaranteed
Term
15-year PPA · 25-year useful life

Grid access

Node
San Francisco 132/33 kV substation
Free capacity
18 MW (CAMMESA, public data)
Requested capacity
10.0 MW
Dispatch priority
Assigned 08/2026 · expires 08/2028
Guarantee deposit
Posted

Energy buyer

Food manufacturer, Villa Mercedes · MATER Large User

15-year MATER PPA · USD 57/MWh

Stages

Land03/2026
Engineering06/2026
Grid access08/2026
todayFinancingcloses 12/15/2026
Construction2027 · 8 months
Operation2028 to 2053

01Equipment and quantities24 lines · total USD 7,350,401 = CAPEX

CategoryDescriptionManufacturer and modelSpecificationQuantityUnit priceTotalSourcePurchase status
Main equipment, item by item · click a row to see warranty, country and datasheet
Minor items, by category
Bill of quantities total · 0.612 USD/Wp over 12.016 MWpUSD 7,350,401

Prices in USD excluding VAT. Supplier, EPC, O&M and trustee names are examples; manufacturers and models are real and their prices are examples.

02Prices and CAPEXUSD 7,350,401 · 0.612 USD/Wp

CategoryUSDUSD/Wp% of totalMarket reference USD/WpPlatform average USD/WpSource
EquipmentUSD 1,701,8100.14223.2 %0.1550.143Contract 79 % · Quote 21 % as of 09/22/2026
StructureUSD 1,529,0390.12720.8 %0.1250.119Contract as of 10/05/2026
Electrical BOSUSD 857,0210.07111.7 %0.0800.077Contract 82 % · ELAP estimate 18 % as of 10/05/2026
Medium voltageUSD 454,9900.0386.2 %0.0350.046Contract 13 % · Quote 24 % · ELAP estimate 63 % as of 10/05/2026
Civil worksUSD 699,8210.0589.5 %0.0600.062Contract as of 10/05/2026
Grid connectionUSD 807,5200.06711.0 %0.0500.060Contract as of 10/05/2026
EngineeringUSD 144,1940.0122.0 %0.0120.012ELAP estimate as of 09/15/2026
DevelopmentUSD 546,3310.0457.4 %0.0350.037Contract 60 % · ELAP estimate 40 % as of 10/10/2026
TrusteeUSD 30,0000.0020.4 %0.0030.004Contract as of 10/10/2026
InsuranceUSD 27,2260.0020.4 %0.0020.002Quote as of 10/08/2026
Platform feeUSD 114,0000.0091.6 %0.0100.010Contract as of 07/01/2026
ContingencyUSD 242,0080.0203.3 %0.0200.020ELAP estimate as of 09/15/2026
Financing costUSD 106,7510.0091.5 %0.0120.010ELAP estimate as of 09/15/2026
TaxesUSD 89,6900.0071.2 %0.0080.008ELAP estimate as of 09/15/2026
TotalUSD 7,350,4010.612100 %0.6070.612Contract 76 % · Quote 7 % · ELAP estimate 17 % as of 10/10/2026

Market reference: ELAP estimate ELAP · 2026 market reference, 19 budget prices · 09/15/2026. The platform average is that of the other 6 projects on this page. Each category is the sum of its lines in the bill of quantities.

03Open tenderanonymous until awarded, named afterwards

Equipment · Bifacial module 545 Wp or higher, tier 1Awarded on 09/22/2026 · 22,048 pcs · 3 quotes
BidderOfferUnit priceTotalVersus lowestLead timeResult

Why it won: Not the cheapest (3 % above C), but delivers in 14 weeks versus 22 and accepts the trust's 18 installments.

Structure · Single-row 1P tracker, 52 modulesAwarded on 09/18/2026 · 424 tables · 3 quotes
BidderOfferUnit priceTotalVersus lowestLead timeResult

Why it won: The only offer contributing 100 % of the supply for equity; price within 2 % of the cheapest.

Equipment · String inverter 250 kW, 1,500 VOpen · closes 10/30/2026 · 40 pcs · 2 quotes
BidderOfferUnit priceTotalVersus lowestLead timeResult
Medium voltage · XLPE cable 18/30 kV 1 × 185 mm² AlOpen · closes 11/06/2026 · 7,500 m · 2 quotes
BidderOfferUnit priceTotalVersus lowestLead timeResult

04Use of fundsUSD 0 disbursed of USD 5,925,105

SourcesUSD%
Land, in kindUSD 300,0004.1 %
Equipment, in kindUSD 1,125,29615.3 %
CrowdUSD 3,800,00051.7 %
Bank debtUSD 2,125,10528.9 %
TotalUSD 7,350,401100 %
UsesUSD%
EquipmentUSD 1,701,81023.2 %
StructureUSD 1,529,03920.8 %
Electrical BOSUSD 857,02111.7 %
Medium voltageUSD 454,9906.2 %
Civil worksUSD 699,8219.5 %
Grid connectionUSD 807,52011.0 %
EngineeringUSD 144,1942.0 %
DevelopmentUSD 546,3317.4 %
TrusteeUSD 30,0000.4 %
InsuranceUSD 27,2260.4 %
Platform feeUSD 114,0001.6 %
ContingencyUSD 242,0083.3 %
Financing costUSD 106,7511.5 %
TaxesUSD 89,6901.2 %
TotalUSD 7,350,401100 %

In-kind contributions (USD 1,425,296: land and equipment for equity) do not go through the account. The rest is paid from the trust account against certified milestones by the independent engineer, and every disbursement is published here.

DateMilestoneAmountUseCertificateStatus
12/20/2026Financing closeUSD 534,525Engineering, development, trustee and placement feeon certificationPlanned
02/20/2027EPC signing and advanceUSD 808,587EPC advanceon certificationPlanned
03/20/2027Modules delivered to siteUSD 1,617,174Modules and inverters on deliveryon certificationPlanned
04/20/2027Pile drivingUSD 646,870Pile driving and structureon certificationPlanned
05/20/2027Mechanical installationUSD 700,775Mechanical installationon certificationPlanned
06/20/2027Electrical installationUSD 646,870Electrical BOS and cableson certificationPlanned
07/20/2027MV station and lineUSD 539,058MV stations, line and outgoing bayon certificationPlanned
08/20/2027CAMMESA commercial operationUSD 431,246EPC balance, contingency and retentionon certificationPlanned
Total through the trust accountUSD 5,925,105CAPEX minus in-kind contributions

05Who gets paid whatUSD 822,691 one-off · USD 357,896 per year

PartyWhoItemBasisAmount USDWhenSource
PlatformMercado SolarPlacement fee3 % of the crowd raise, once at closeUSD 114,000OnceContract Platform terms, art. 9 · 07/01/2026
PlatformMercado SolarAdministration and secondary market1 % of revenue, per yearUSD 14,261Per yearContract Platform terms, art. 10 · 07/01/2026
ELAPELAPEngineering0.012 USD/WpUSD 144,194OnceContract Trust agreement, annex III · 10/10/2026
ELAPELAPDevelopment0.018 USD/WpUSD 216,291OnceContract Trust agreement, annex III · 10/10/2026
TrusteeFiduciaria Pampa S.A. (example)Trust formationfixed feeUSD 30,000OnceContract Trust agreement, annex III · 10/10/2026
TrusteeFiduciaria Pampa S.A. (example)Trust administration0.8 % of revenue, per yearUSD 11,409Per yearContract Trust agreement, annex III · 10/10/2026
EPCConstructora Huarpe (example)EPC's declared margin10 % of the works in its scope (included in the bill of quantities)USD 266,915OnceContract Trust agreement, annex III · 10/10/2026
O&MOperadora Solar Andes (example)Operation and maintenanceUSD 13,500 per MWp per yearUSD 162,218Per yearContract Trust agreement, annex III · 10/10/2026
BankBanco Regional (example)Debt structuring1 % of the debtUSD 21,251OnceContract Trust agreement, annex III · 10/10/2026
BankBanco Regional (example)Year-1 interest8 % a year on the debtUSD 170,008Per yearContract Trust agreement, annex III · 10/10/2026
Independent engineerEstudio Ingeniería Zonda (example)Technical review and construction certificationUSD 2,500 per MWpUSD 30,040OnceContract Trust agreement, annex III · 10/10/2026
One-off, within CAPEXUSD 822,69111.2 % of CAPEX
Annual, year 1USD 357,896from the payment waterfall
Declared conflict of interest. ELAP is at once engineer, developer and platform of this project: it charges for engineering, development and the platform fees. That is why the technical review is signed by an independent engineer (Estudio Ingeniería Zonda (example)), who also certifies every milestone before a disbursement.

06Production and assumptionsP50 25.83 GWh · P90 24.15 GWh per year · Source: ELAP estimate · ELAP · report rev B · P50/P90 study · 09/15/2026

Data or assumptionValue
P50 production25.83 GWh per year · 2,150 kWh/kWp
P90 production24.15 GWh per year · 2,010 kWh/kWp
Weather data sourcePVGIS-SARAH3 cross-checked with Solcast
Years in the series2005 to 2023 (19 years)
Global horizontal irradiation (GHI)2,010 kWh/m² per year
Bifacial gain7.5 %
Total system losses14.2 %
Soiling2.0 % with quarterly cleaning
Availability99.0 %
Grid curtailment3.0 %
Annual module degradation0.4 % per year (manufacturer's linear warranty)
Combined uncertainty (1 σ)5.1 % · P90 = P50 × (1 − 1.28 σ)
Download ELAP's P50/P90 studyPDF of report rev B, with the weather series and the loss breakdown.

07Revenue15-year MATER PPA

ItemValueSource
PriceUSD 57/MWhContract Signed MATER PPA · 08/28/2026
Term15 years from commercial operationContract Signed MATER PPA · 08/28/2026
IndexationNo indexation: fixed price in USDContract Signed MATER PPA · 08/28/2026
CounterpartyFood manufacturer, Villa Mercedes · MATER Large User · A rating (example)Contract Signed MATER PPA · 08/28/2026
GuaranteesLetter of credit for 3 months of billingContract Signed MATER PPA · 08/28/2026
Energy covered85 % of the energy; the remaining 15 % on the spot marketContract Signed MATER PPA · 08/28/2026
After the contractSpot, USD 45/MWh as an exampleELAP estimate ELAP · report rev B · 09/15/2026

08Payment waterfallyear 1 · projected

OrderItemBasisUSD year 1, P50% of revenueUSD year 1, P90Source
Energy sales revenue25.83 GWh · 85 % at USD 57/MWh and 15 % at USD 45/MWhUSD 1,426,078100.0 %USD 1,315,103Contract Signed MATER PPA · 08/28/2026
1Operation and maintenanceUSD 13,500 per MWp per year−USD 162,21811.4 %−USD 162,218Contract Trust agreement, annex III · 10/10/2026
2Operational all-risk insurance0.3 % of CAPEX per year−USD 22,0511.5 %−USD 22,051ELAP estimate ELAP · trust model, report rev B · 09/15/2026
3Trustee fee0.8 % of revenue−USD 11,4090.8 %−USD 10,521Contract Trust agreement, annex III · 10/10/2026
4Platform administration fee1 % of revenue−USD 14,2611.0 %−USD 13,151Contract Platform terms, art. 10 · 07/01/2026
5Municipal fees and gross receipts tax1.2 % of revenue−USD 17,1131.2 %−USD 15,781ELAP estimate ELAP · trust model, report rev B · 09/15/2026
6Income tax35 % of profit, with 25-year depreciation−USD 257,25118.0 %−USD 219,575ELAP estimate ELAP · trust model, report rev B · 09/15/2026
7Debt service (principal and interest)USD 2.13 M at 8 % over 10 years−USD 316,70322.2 %−USD 316,703Contract Trust agreement, annex III · 10/10/2026
8Inverter replacement reserveUSD 3,000 per MWp per year−USD 36,0482.5 %−USD 36,048ELAP estimate ELAP · trust model, report rev B · 09/15/2026
9Distribution to investors11.3 % of contributed capitalUSD 589,02441.3 %USD 519,054ELAP estimate ELAP · trust model, report rev B · 09/15/2026

First operation, taxes and debt; then reserves; and only after that the investors. The return on the sheet is the last line divided by the contributed capital (USD 5,225,296).

09Sensitivityyear 1 · same model as the payment waterfall · Source: ELAP estimate · ELAP · trust model, report rev B · 09/15/2026

CaseYear-1 returnVersus baseDistribution USDPer USD 1,000
Base case (P50)11.3 %—USD 589,024USD 113
Sale price −10 %9.6 %−1.7 ppUSD 499,110USD 96
P90 production9.9 %−1.3 ppUSD 519,054USD 99
CAPEX +10 %, with more debt9.7 %−1.5 ppUSD 508,919USD 97
20 % exchange-rate gap9.4 %−1.9 ppUSD 490,853USD 94

CAPEX +10 %: the overrun is financed with more debt. Exchange-rate gap: revenue is collected in pesos at the official rate and the investor converts to dollars at a rate 20 % higher.

10Construction progressplanned schedule · Source: ELAP estimate · ELAP · report rev B · schedule · 09/15/2026

MilestonePlannedActualDelay
EPC signing and advance01/15/2027pending—
Modules delivered to site03/15/2027pending—
Pile driving04/15/2027pending—
Mechanical installation05/15/2027pending—
Electrical installation06/15/2027pending—
MV station and line07/15/2027pending—
Energization08/15/2027pending—
CAMMESA commercial operation09/15/2027pending—
Main equipmentOf 8
Awarded or later2
Purchased0
Delivered to site0
Installed0
MonthPlannedActualCurve
01/20270 %—
02/20274 %—
03/202716 %—
04/202732 %—
05/202750 %—
06/202768 %—
07/202784 %—
08/202796 %—
09/2027100 %—

Purchase status of each item in section 1. Actual dates and progress: independent engineer's certificates.

11Change logpublic to everyone

DateWhat changedFromToWhySource
09/15/2026Modulesrev A · 22,020 modulesrev B · 22,048 modulesRev B of the ELAP report: the layout is adjusted to whole tables of 52 modules.ELAP estimate ELAP · report rev B · 09/15/2026
09/18/2026Trackers: price and sourceELAP estimate · USD 2,710 per tableContract · USD 2,654 per tableTender awarded to Trackers del Oeste (example), in-kind contribution for equity.Contract Contribution agreement no. 3 · 09/18/2026
09/22/2026Modules: sourceQuote · USD 0.112/WpContract · USD 0.112/WpPurchase order no. 14 to Importadora Andina (example).Contract Purchase order no. 14 · 09/22/2026

When a figure changes source (estimated, quoted, contracted, actual), the previous one stays here.

12Documentsdata room

  • Trust agreementPDF · 10/2026Registered users only
  • ProspectusPDF · 10/2026View
  • Power purchase agreementPDF · 08/2026 · term sheetRegistered users only
  • ELAP engineering report, rev BPDF · 09/2026View
  • Grid access studyPDF · 08/2026 · CAMMESA priority noteView
  • Independent engineer's technical auditPending
  • Quarterly financial statements of the trustPending
  • P50/P90 production studyPDF · 09/2026View
  • Plant layout and single-line diagram ELE-SLD-01PDF · 09/2026View
  • Bill of quantities and budgetXLSX · 09/2026Registered users only
  • EPC bidPDF · 09/2026Registered users only
  • All-risk policyPending