Córdoba · Villa DoloresFinancing
PSF Villa Dolores
1.2 MWp · 2V fixed structure · 25° · Distributed generation · Law 27,424 · USD 62/MWh
Key factskey information sheet · all figures are examples
| Item | Value | Source |
|---|---|---|
| What it is | 1.22 MWp (1.0 MWac) solar plant in Villa Dolores, Córdoba · 2V fixed structure · 25° · sells its energy under Distributed generation · Law 27,424 at USD 62/MWh | ELAP estimate ELAP · report rev B · P50/P90 study · 06/20/2026 |
| Amount being raised | USD 0.55 M from the crowd, out of a CAPEX of USD 0.74 M (USD 0.605/Wp) · 23 % raised · closes 02/28/2027 | Contract 21 % · Quote 55 % · ELAP estimate 24 % as of 10/20/2026 |
| Minimum ticket | USD 300 · 3 shares of USD 100, upfront or in installments | Contract Platform terms, art. 9 · 07/01/2026 |
| Return | P50 9.8 % · P90 8.9 % of contributed capital in year 1 · projected, not guaranteed | ELAP estimate ELAP · trust model, report rev B · 06/20/2026 |
| Term | 20-year self-consumption · 25-year useful life | Contract Self-consumption contract · 07/15/2026 |
| Main risks | Single buyer · Tariff | ELAP estimate ELAP · report rev B · P50/P90 study · 06/20/2026 |
| Total fees | USD 91,976 one-off (12.5 % of CAPEX) · USD 26,688 per year (20.7 % of year-1 revenue, including debt interest) | Quote EPC bid and trustee's proposal · 10/01/2026 |
[Model: key information sheet under EU Regulation 2020/1503 and CNV RG 717/2018 · to be checked in the legal memo]
Who takes part
| Role | Who | Contribution | Status |
|---|---|---|---|
| Land | Meat-packing plant (own premises) | Provides the space at no cost | Ready |
| Modules | Importadora Andina (example) | In-kind contribution for equity | Ready |
| Buyer | Meat-packing plant, Villa Dolores | 78 % self-consumption · surplus to the distribution company | Ready |
| EPC | Instalador Kaiken (example) | Turnkey · bid | In progress |
| Engineering | ELAP | rev B | Ready |
Capital structure example
Total USD 0.74 M = CAPEX, sum of the bill of quantities · USD 0.605/Wp · contributed capital (excluding debt) USD 0.69 M
Explicit risks
| Risk | What can happen | What limits it |
|---|---|---|
| Single buyer | Revenue depends on the meat-packing plant's consumption. | High reference tariff; the surplus is sold to the distribution company at a lower price. |
| Tariff | The price is the avoided tariff: if the tariff falls, revenue falls. | The sensitivity shows the price −10 %. |
Questions
No questions yet.
Financing closes 02/28/2027
- Return
- 8.9 to 9.8 % in year 1 (P90 to P50), projected, not guaranteed
- Term
- 20-year self-consumption · 25-year useful life
Grid access
- Node
- Distribution company grid · 13.2 kV
- Free capacity
- 3 MW (CAMMESA, public data)
- Requested capacity
- 1.0 MW
- Dispatch priority
- Not applicable (DG) · distribution company authorization obtained
- Guarantee deposit
- Not applicable
Energy buyer
Meat-packing plant, Villa Dolores · user-generator, surplus to the distribution company
Distributed generation · Law 27,424 · USD 62/MWh
Stages
01Equipment and quantities21 lines · total USD 736,016 = CAPEX
| Category | Description | Manufacturer and model | Specification | Quantity | Unit price | Total | Source | Purchase status |
|---|---|---|---|---|---|---|---|---|
| Main equipment, item by item · click a row to see warranty, country and datasheet | ||||||||
| Equipment | Monofacial PV module | LONGiHi-MO 6 LR5-72HTH-585M | 585 Wp · monofacial · 1,500 V | 2,080 pcs | USD 67.28 | USD 139,942 | Contract Contribution agreement no. 1 · Importadora Andina (example) · 09/10/2026 | Awarded |
| Equipment | String inverter | HuaweiSUN2000-100KTL-M2 | 100 kW · 1,100 V · 10 MPPT | 10 pcs | USD 4,300 | USD 43,000 | Quote Supplier A · 09/25/2026 · expires 11/05/2026 | Quoted |
| Structure | Driven 2V fixed structure | Local manufacturing2V · 40 módulos · 25° | hot-dip galvanized steel | 52 tables | USD 1,405 | USD 73,060 | Quote Supplier B · 10/20/2026 · expires 11/19/2026 | Quoted |
| Medium voltage | Oil-immersed power transformer | Tadeo CzerwenyTPC 1250 kVA ONAN | 1.25 MVA · 13.2/0.4 kV · Dyn11 | 1 pcs | USD 32,000 | USD 32,000 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Medium voltage | Medium-voltage switchgear, 2 functions | Ormazabalcgm.3 24 kV | 24 kV · line + protection | 1 pcs | USD 24,000 | USD 24,000 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Electrical BOS | DC solar cable | PrysmianTecsun H1Z2Z2-K | 1 × 6 mm² · 1.5 kV | 5,200 m | USD 0.95 | USD 4,940 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Electrical BOS | Low-voltage cable, inverter to switchboard | IMSASubterráneo XLPE Cu | 1 × 95 mm² · 1.1 kV | 3,000 m | USD 9.40 | USD 28,200 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Minor items, by category | ||||||||
| Structure | Pile driving and installation of the fixed structure | — | 0.024 USD/Wp | 1 lump sum | USD 36,504 | USD 36,504 | Quote Instalador Kaiken (example) · turnkey bid · 09/30/2026 · expires 11/29/2026 | Quoted |
| Electrical BOS | String boxes, protection, earthing, monitoring and electrical installation | — | 0.052 USD/Wp | 1 lump sum | USD 79,092 | USD 79,092 | Quote Instalador Kaiken (example) · turnkey bid · 09/30/2026 · expires 11/29/2026 | Quoted |
| Medium voltage | Housing, foundations and installation of the MV stations | — | per station | 1 pcs | USD 32,500 | USD 32,500 | Quote Instalador Kaiken (example) · turnkey bid · 09/30/2026 · expires 11/29/2026 | Quoted |
| Civil works | Earthworks, internal roads, fencing, drainage and site compound | — | 0.052 USD/Wp | 1 lump sum | USD 79,092 | USD 79,092 | Quote Instalador Kaiken (example) · turnkey bid · 09/30/2026 · expires 11/29/2026 | Quoted |
| Grid connection | Connection to the site switchboard and bidirectional metering | — | 13.2 kV | 1 lump sum | USD 47,500 | USD 47,500 | Quote Instalador Kaiken (example) · turnkey bid · 09/30/2026 · expires 11/29/2026 | Quoted |
| Engineering | ELAP engineering: basic, detailed, P50/P90 and as-built | — | 0.012 USD/Wp | 1 lump sum | USD 14,602 | USD 14,602 | ELAP estimate ELAP · report rev B · 06/20/2026 | Purchased |
| Development | ELAP development: permits, environmental impact and dispatch priority management | — | 0.018 USD/Wp | 1 lump sum | USD 21,902 | USD 21,902 | ELAP estimate ELAP · report rev B · 06/20/2026 | Purchased |
| Development | Independent engineer: design review and construction certification | — | USD 2,500 per MWp | 1 lump sum | USD 3,042 | USD 3,042 | Quote Fiduciaria Pampa S.A. (example) · 10/01/2026 · expires 12/31/2026 | Awarded |
| Trustee | Trust formation and legal structuring | — | fixed fee | 1 lump sum | USD 8,000 | USD 8,000 | Quote Fiduciaria Pampa S.A. (example) · 10/01/2026 · expires 12/31/2026 | Purchased |
| Insurance | All-risk construction and transport insurance | — | 0.45 % of construction | 1 lump sum | USD 2,789 | USD 2,789 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Platform fee | Platform placement fee | — | 3 % of the crowd raise | 1 lump sum | USD 16,500 | USD 16,500 | Contract Platform terms, art. 9 · 07/01/2026 | Awarded |
| Contingency | Construction contingency | — | 4 % of construction | 1 lump sum | USD 24,793 | USD 24,793 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Financing cost | Cost of investor installments and debt structuring | — | 5 % of the amount paid in installments + 1 % of the debt | 1 lump sum | USD 14,211 | USD 14,211 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Taxes | Import duties, statistics fee and non-recoverable taxes | — | 5 % of imports from outside Mercosur | 1 lump sum | USD 10,347 | USD 10,347 | ELAP estimate ELAP · report rev B · 06/20/2026 | To quote |
| Bill of quantities total · 0.605 USD/Wp over 1.217 MWp | USD 736,016 | |||||||
Prices in USD excluding VAT. Supplier, EPC, O&M and trustee names are examples; manufacturers and models are real and their prices are examples.
02Prices and CAPEXUSD 736,016 · 0.605 USD/Wp
| Category | USD | USD/Wp | % of total | Market reference USD/Wp | Platform average USD/Wp | Source |
|---|---|---|---|---|---|---|
| Equipment | USD 182,942 | 0.150 | 24.9 % | 0.155 | 0.142 | Contract 76 % · Quote 24 % as of 09/25/2026 |
| Structure | USD 109,564 | 0.090 | 14.9 % | 0.125 | 0.126 | Quote as of 10/20/2026 |
| Electrical BOS | USD 112,232 | 0.092 | 15.2 % | 0.080 | 0.074 | Quote 70 % · ELAP estimate 30 % as of 09/30/2026 |
| Medium voltage | USD 88,500 | 0.073 | 12.0 % | 0.035 | 0.041 | Quote 37 % · ELAP estimate 63 % as of 09/30/2026 |
| Civil works | USD 79,092 | 0.065 | 10.7 % | 0.060 | 0.061 | Quote as of 09/30/2026 |
| Grid connection | USD 47,500 | 0.039 | 6.5 % | 0.050 | 0.064 | Quote as of 09/30/2026 |
| Engineering | USD 14,602 | 0.012 | 2.0 % | 0.012 | 0.012 | ELAP estimate as of 06/20/2026 |
| Development | USD 24,944 | 0.020 | 3.4 % | 0.035 | 0.041 | Quote 12 % · ELAP estimate 88 % as of 10/01/2026 |
| Trustee | USD 8,000 | 0.007 | 1.1 % | 0.003 | 0.003 | Quote as of 10/01/2026 |
| Insurance | USD 2,789 | 0.002 | 0.4 % | 0.002 | 0.002 | ELAP estimate as of 06/20/2026 |
| Platform fee | USD 16,500 | 0.014 | 2.2 % | 0.010 | 0.010 | Contract as of 07/01/2026 |
| Contingency | USD 24,793 | 0.020 | 3.4 % | 0.020 | 0.020 | ELAP estimate as of 06/20/2026 |
| Financing cost | USD 14,211 | 0.012 | 1.9 % | 0.012 | 0.009 | ELAP estimate as of 06/20/2026 |
| Taxes | USD 10,347 | 0.009 | 1.4 % | 0.008 | 0.008 | ELAP estimate as of 06/20/2026 |
| Total | USD 736,016 | 0.605 | 100 % | 0.607 | 0.613 | Contract 21 % · Quote 55 % · ELAP estimate 24 % as of 10/20/2026 |
Market reference: ELAP estimate ELAP · 2026 market reference, 19 budget prices · 09/15/2026. The platform average is that of the other 6 projects on this page. Each category is the sum of its lines in the bill of quantities.
03Open tenderanonymous until awarded, named afterwards
| Bidder | Offer | Unit price | Total | Versus lowest | Lead time | Result |
|---|---|---|---|---|---|---|
| Supplier A | 2V 40 modules, driven | USD 1,460 | USD 75,920 | +5.2 % | 8 wk | Under evaluation |
| Supplier B | 2V 40 modules, driven | USD 1,405 | USD 73,060 | +1.2 % | 9 wk | Under evaluation |
| Supplier C | 2V 40 modules, ground screws | USD 1,530 | USD 79,560 | +10.2 % | 6 wk | Under evaluation |
| Supplier D | 2V 40 modules, driven | USD 1,388 | USD 72,176 | lowest | 12 wk | Under evaluation |
| Bidder | Offer | Unit price | Total | Versus lowest | Lead time | Result |
|---|---|---|---|---|---|---|
| Supplier A | Huawei SUN2000-100KTL-M2 | USD 4,300 | USD 43,000 | lowest | 6 wk | Under evaluation |
04Use of fundsUSD 0 disbursed of USD 596,074
| Sources | USD | % |
|---|---|---|
| Land, in kind | USD 0 | 0.0 % |
| Equipment, in kind | USD 139,942 | 19.0 % |
| Crowd | USD 550,000 | 74.7 % |
| Bank debt | USD 46,074 | 6.3 % |
| Total | USD 736,016 | 100 % |
| Uses | USD | % |
|---|---|---|
| Equipment | USD 182,942 | 24.9 % |
| Structure | USD 109,564 | 14.9 % |
| Electrical BOS | USD 112,232 | 15.2 % |
| Medium voltage | USD 88,500 | 12.0 % |
| Civil works | USD 79,092 | 10.7 % |
| Grid connection | USD 47,500 | 6.5 % |
| Engineering | USD 14,602 | 2.0 % |
| Development | USD 24,944 | 3.4 % |
| Trustee | USD 8,000 | 1.1 % |
| Insurance | USD 2,789 | 0.4 % |
| Platform fee | USD 16,500 | 2.2 % |
| Contingency | USD 24,793 | 3.4 % |
| Financing cost | USD 14,211 | 1.9 % |
| Taxes | USD 10,347 | 1.4 % |
| Total | USD 736,016 | 100 % |
In-kind contributions (USD 139,942: land and equipment for equity) do not go through the account. The rest is paid from the trust account against certified milestones by the independent engineer, and every disbursement is published here.
| Date | Milestone | Amount | Use | Certificate | Status |
|---|---|---|---|---|---|
| 03/20/2027 | Financing close | USD 64,046 | Engineering, development, trustee and placement fee | on certification | Planned |
| 05/20/2027 | EPC signing and advance | USD 79,804 | EPC advance | on certification | Planned |
| 06/20/2027 | Modules delivered to site | USD 159,608 | Modules and inverters on delivery | on certification | Planned |
| 07/20/2027 | Pile driving | USD 63,843 | Pile driving and structure | on certification | Planned |
| 08/20/2027 | Mechanical installation | USD 69,164 | Mechanical installation | on certification | Planned |
| 09/20/2027 | Electrical installation | USD 63,843 | Electrical BOS and cables | on certification | Planned |
| 10/20/2027 | MV station and line | USD 53,203 | MV stations, line and outgoing bay | on certification | Planned |
| 11/20/2027 | CAMMESA commercial operation | USD 42,563 | EPC balance, contingency and retention | on certification | Planned |
| Total through the trust account | USD 596,074 | CAPEX minus in-kind contributions | |||
05Who gets paid whatUSD 91,976 one-off · USD 26,688 per year
| Party | Who | Item | Basis | Amount USD | When | Source |
|---|---|---|---|---|---|---|
| Platform | Mercado Solar | Placement fee | 3 % of the crowd raise, once at close | USD 16,500 | Once | Contract Platform terms, art. 9 · 07/01/2026 |
| Platform | Mercado Solar | Administration and secondary market | 1 % of revenue, per year | USD 1,287 | Per year | Contract Platform terms, art. 10 · 07/01/2026 |
| ELAP | ELAP | Engineering | 0.012 USD/Wp | USD 14,602 | Once | Quote EPC bid and trustee's proposal · 10/01/2026 |
| ELAP | ELAP | Development | 0.018 USD/Wp | USD 21,902 | Once | Quote EPC bid and trustee's proposal · 10/01/2026 |
| Trustee | Fiduciaria Pampa S.A. (example) | Trust formation | fixed fee | USD 8,000 | Once | Quote EPC bid and trustee's proposal · 10/01/2026 |
| Trustee | Fiduciaria Pampa S.A. (example) | Trust administration | 0.8 % of revenue, per year | USD 1,029 | Per year | Quote EPC bid and trustee's proposal · 10/01/2026 |
| EPC | Instalador Kaiken (example) | EPC's declared margin | 10 % of the works in its scope (included in the bill of quantities) | USD 27,469 | Once | Quote EPC bid and trustee's proposal · 10/01/2026 |
| O&M | Instalador Kaiken (example) | Operation and maintenance | USD 17,000 per MWp per year | USD 20,686 | Per year | Quote EPC bid and trustee's proposal · 10/01/2026 |
| Bank | Banco Regional (example) | Debt structuring | 1 % of the debt | USD 461 | Once | Quote EPC bid and trustee's proposal · 10/01/2026 |
| Bank | Banco Regional (example) | Year-1 interest | 8 % a year on the debt | USD 3,686 | Per year | Quote EPC bid and trustee's proposal · 10/01/2026 |
| Independent engineer | Estudio Ingeniería Zonda (example) | Technical review and construction certification | USD 2,500 per MWp | USD 3,042 | Once | Quote EPC bid and trustee's proposal · 10/01/2026 |
| One-off, within CAPEX | USD 91,976 | 12.5 % of CAPEX | ||||
| Annual, year 1 | USD 26,688 | from the payment waterfall | ||||
06Production and assumptionsP50 2.25 GWh · P90 2.12 GWh per year · Source: ELAP estimate · ELAP · report rev B · P50/P90 study · 06/20/2026
| Data or assumption | Value |
|---|---|
| P50 production | 2.25 GWh per year · 1,850 kWh/kWp |
| P90 production | 2.12 GWh per year · 1,740 kWh/kWp |
| Weather data source | PVGIS-SARAH3 |
| Years in the series | 2005 to 2023 (19 years) |
| Global horizontal irradiation (GHI) | 1,890 kWh/m² per year |
| Bifacial gain | not applicable (monofacial) |
| Total system losses | 13.8 % |
| Soiling | 2.0 % with quarterly cleaning |
| Availability | 99.0 % |
| Grid curtailment | 0.0 % |
| Annual module degradation | 0.4 % per year (manufacturer's linear warranty) |
| Combined uncertainty (1 σ) | 4.6 % · P90 = P50 × (1 − 1.28 σ) |
07RevenueDistributed generation · Law 27,424
| Item | Value | Source |
|---|---|---|
| Price | USD 62/MWh: the meat-packing plant's avoided tariff | Contract Self-consumption contract · 07/15/2026 |
| Term | 20 years | Contract Self-consumption contract · 07/15/2026 |
| Indexation | Follows the distribution company's tariff | Contract Self-consumption contract · 07/15/2026 |
| Counterparty | Meat-packing plant, Villa Dolores | Contract Self-consumption contract · 07/15/2026 |
| Guarantees | Direct debit and a 2-month deposit | Contract Self-consumption contract · 07/15/2026 |
| Energy covered | 78 % self-consumption; 22 % surplus to the distribution company at USD 40/MWh | ELAP estimate ELAP · report rev B · 06/20/2026 |
| After the contract | Same scheme until the end of the useful life | ELAP estimate ELAP · report rev B · 06/20/2026 |
08Payment waterfallyear 1 · projected
| Order | Item | Basis | USD year 1, P50 | % of revenue | USD year 1, P90 | Source |
|---|---|---|---|---|---|---|
| Energy sales revenue | 2.25 GWh · 78 % at USD 62/MWh and 22 % at USD 40/MWh | USD 128,672 | 100.0 % | USD 119,158 | Contract Self-consumption contract · 07/15/2026 | |
| 1 | Operation and maintenance | USD 17,000 per MWp per year | −USD 20,686 | 16.1 % | −USD 20,686 | Quote EPC bid and trustee's proposal · 10/01/2026 |
| 2 | Operational all-risk insurance | 0.3 % of CAPEX per year | −USD 2,208 | 1.7 % | −USD 2,208 | ELAP estimate ELAP · trust model, report rev B · 06/20/2026 |
| 3 | Trustee fee | 0.8 % of revenue | −USD 1,029 | 0.8 % | −USD 953 | Quote EPC bid and trustee's proposal · 10/01/2026 |
| 4 | Platform administration fee | 1 % of revenue | −USD 1,287 | 1.0 % | −USD 1,192 | Contract Platform terms, art. 10 · 07/01/2026 |
| 5 | Municipal fees and gross receipts tax | 1.2 % of revenue | −USD 1,544 | 1.2 % | −USD 1,430 | ELAP estimate ELAP · trust model, report rev B · 06/20/2026 |
| 6 | Income tax | 35 % of profit, with 25-year depreciation | −USD 24,077 | 18.7 % | −USD 20,847 | ELAP estimate ELAP · trust model, report rev B · 06/20/2026 |
| 7 | Debt service (principal and interest) | USD 0.05 M at 8 % over 10 years | −USD 6,866 | 5.3 % | −USD 6,866 | Quote EPC bid and trustee's proposal · 10/01/2026 |
| 8 | Inverter replacement reserve | USD 3,000 per MWp per year | −USD 3,650 | 2.8 % | −USD 3,650 | ELAP estimate ELAP · trust model, report rev B · 06/20/2026 |
| 9 | Distribution to investors | 9.8 % of contributed capital | USD 67,324 | 52.3 % | USD 61,326 | ELAP estimate ELAP · trust model, report rev B · 06/20/2026 |
First operation, taxes and debt; then reserves; and only after that the investors. The return on the sheet is the last line divided by the contributed capital (USD 689,942).
09Sensitivityyear 1 · same model as the payment waterfall · Source: ELAP estimate · ELAP · trust model, report rev B · 06/20/2026
| Case | Year-1 return | Versus base | Distribution USD | Per USD 1,000 |
|---|---|---|---|---|
| Base case (P50) | 9.8 % | — | USD 67,324 | USD 98 |
| Sale price −10 % | 8.6 % | −1.2 pp | USD 59,211 | USD 86 |
| P90 production | 8.9 % | −0.9 pp | USD 61,326 | USD 89 |
| CAPEX +10 %, with more debt | 8.6 % | −1.2 pp | USD 59,303 | USD 86 |
| 20 % exchange-rate gap | 8.1 % | −1.6 pp | USD 56,103 | USD 81 |
CAPEX +10 %: the overrun is financed with more debt. Exchange-rate gap: revenue is collected in pesos at the official rate and the investor converts to dollars at a rate 20 % higher.
10Construction progressplanned schedule · Source: ELAP estimate · ELAP · report rev B · schedule · 06/20/2026
| Milestone | Planned | Actual | Delay |
|---|---|---|---|
| EPC signing and advance | 04/15/2027 | pending | — |
| Modules delivered to site | 06/15/2027 | pending | — |
| Pile driving | 07/15/2027 | pending | — |
| Mechanical installation | 08/15/2027 | pending | — |
| Electrical installation | 09/15/2027 | pending | — |
| MV station and line | 10/15/2027 | pending | — |
| Energization | 11/15/2027 | pending | — |
| CAMMESA commercial operation | 12/15/2027 | pending | — |
| Main equipment | Of 7 |
|---|---|
| Awarded or later | 1 |
| Purchased | 0 |
| Delivered to site | 0 |
| Installed | 0 |
| Month | Planned | Actual | Curve |
|---|---|---|---|
| 04/2027 | 0 % | — | |
| 05/2027 | 10 % | — | |
| 06/2027 | 35 % | — | |
| 07/2027 | 65 % | — | |
| 08/2027 | 90 % | — | |
| 09/2027 | 100 % | — |
Purchase status of each item in section 1. Actual dates and progress: independent engineer's certificates.
11Change logpublic to everyone · Source: Contract · Contribution agreement no. 1 · 09/10/2026
| Date | What changed | From | To | Why |
|---|---|---|---|---|
| 09/10/2026 | Modules: price and source | ELAP estimate · USD 0.110/Wp | Contract · USD 0.115/Wp | In-kind contribution for equity by Importadora Andina (example). |
When a figure changes source (estimated, quoted, contracted, actual), the previous one stays here.
12Documentsdata room
- Trust agreementPending
- ProspectusPDF · 10/2026View
- Power purchase agreementPDF · 07/2026 · self-consumption contractRegistered users only
- ELAP engineering report, rev BPDF · 06/2026View
- Grid access studyPDF · 07/2026 · distribution company authorizationView
- Independent engineer's technical auditPending
- Quarterly financial statements of the trustPending