Córdoba · Villa DoloresFinancing

PSF Villa Dolores

1.2 MWp · 2V fixed structure · 25° · Distributed generation · Law 27,424 · USD 62/MWh

Back to explore

Key factskey information sheet · all figures are examples

ItemValueSource
What it is1.22 MWp (1.0 MWac) solar plant in Villa Dolores, Córdoba · 2V fixed structure · 25° · sells its energy under Distributed generation · Law 27,424 at USD 62/MWhELAP estimate ELAP · report rev B · P50/P90 study · 06/20/2026
Amount being raisedUSD 0.55 M from the crowd, out of a CAPEX of USD 0.74 M (USD 0.605/Wp) · 23 % raised · closes 02/28/2027Contract 21 % · Quote 55 % · ELAP estimate 24 % as of 10/20/2026
Minimum ticketUSD 300 · 3 shares of USD 100, upfront or in installmentsContract Platform terms, art. 9 · 07/01/2026
ReturnP50 9.8 % · P90 8.9 % of contributed capital in year 1 · projected, not guaranteedELAP estimate ELAP · trust model, report rev B · 06/20/2026
Term20-year self-consumption · 25-year useful lifeContract Self-consumption contract · 07/15/2026
Main risksSingle buyer · TariffELAP estimate ELAP · report rev B · P50/P90 study · 06/20/2026
Total feesUSD 91,976 one-off (12.5 % of CAPEX) · USD 26,688 per year (20.7 % of year-1 revenue, including debt interest)Quote EPC bid and trustee's proposal · 10/01/2026

[Model: key information sheet under EU Regulation 2020/1503 and CNV RG 717/2018 · to be checked in the legal memo]

TablesMV stationGrid lineSite boundary
Plant — Plan
52 fixed 2V tables of 2 × 201 transformer of 1.25 MVA · 13.2 kVInternal connection on the meat-packing plant's premises2.2 ha within the premisesELAP layout, report revision

Who takes part

RoleWhoContributionStatus
LandMeat-packing plant (own premises)Provides the space at no costReady
ModulesImportadora Andina (example)In-kind contribution for equityReady
BuyerMeat-packing plant, Villa Dolores78 % self-consumption · surplus to the distribution companyReady
EPCInstalador Kaiken (example)Turnkey · bidIn progress
EngineeringELAPrev BReady

Capital structure example

Land, in kind · USD 0.00 M · 0 %Equipment, in kind · USD 0.14 M · 19 %Crowd · USD 0.55 M · 75 %Bank debt · USD 0.05 M · 6 %

Total USD 0.74 M = CAPEX, sum of the bill of quantities · USD 0.605/Wp · contributed capital (excluding debt) USD 0.69 M

P50P90
Annual distribution — % of paid-in capital
0 %5 %10 %15 %20 %debt repaidP50 12.9 %P90 11.7 %1510152025year
Years 1 to 10 with debtRises once the debt is repaidProjected, not guaranteed

Explicit risks

RiskWhat can happenWhat limits it
Single buyerRevenue depends on the meat-packing plant's consumption.High reference tariff; the surplus is sold to the distribution company at a lower price.
TariffThe price is the avoided tariff: if the tariff falls, revenue falls.The sensitivity shows the price −10 %.

Questions

No questions yet.

Financing closes 02/28/2027

23 % · USD 0.13 M of USD 0.55 M · 80 % minimum to close
Minimum ticketUSD 3003 shares · or 12 installments of USD 27 · or 18 of USD 18
Return
8.9 to 9.8 % in year 1 (P90 to P50), projected, not guaranteed
Term
20-year self-consumption · 25-year useful life

Grid access

Node
Distribution company grid · 13.2 kV
Free capacity
3 MW (CAMMESA, public data)
Requested capacity
1.0 MW
Dispatch priority
Not applicable (DG) · distribution company authorization obtained
Guarantee deposit
Not applicable

Energy buyer

Meat-packing plant, Villa Dolores · user-generator, surplus to the distribution company

Distributed generation · Law 27,424 · USD 62/MWh

Stages

Land01/2026
Engineering04/2026
Grid access07/2026
todayFinancingcloses 02/28/2027
Construction2027
Operation2027 to 2052

01Equipment and quantities21 lines · total USD 736,016 = CAPEX

CategoryDescriptionManufacturer and modelSpecificationQuantityUnit priceTotalSourcePurchase status
Main equipment, item by item · click a row to see warranty, country and datasheet
Minor items, by category
Bill of quantities total · 0.605 USD/Wp over 1.217 MWpUSD 736,016

Prices in USD excluding VAT. Supplier, EPC, O&M and trustee names are examples; manufacturers and models are real and their prices are examples.

02Prices and CAPEXUSD 736,016 · 0.605 USD/Wp

CategoryUSDUSD/Wp% of totalMarket reference USD/WpPlatform average USD/WpSource
EquipmentUSD 182,9420.15024.9 %0.1550.142Contract 76 % · Quote 24 % as of 09/25/2026
StructureUSD 109,5640.09014.9 %0.1250.126Quote as of 10/20/2026
Electrical BOSUSD 112,2320.09215.2 %0.0800.074Quote 70 % · ELAP estimate 30 % as of 09/30/2026
Medium voltageUSD 88,5000.07312.0 %0.0350.041Quote 37 % · ELAP estimate 63 % as of 09/30/2026
Civil worksUSD 79,0920.06510.7 %0.0600.061Quote as of 09/30/2026
Grid connectionUSD 47,5000.0396.5 %0.0500.064Quote as of 09/30/2026
EngineeringUSD 14,6020.0122.0 %0.0120.012ELAP estimate as of 06/20/2026
DevelopmentUSD 24,9440.0203.4 %0.0350.041Quote 12 % · ELAP estimate 88 % as of 10/01/2026
TrusteeUSD 8,0000.0071.1 %0.0030.003Quote as of 10/01/2026
InsuranceUSD 2,7890.0020.4 %0.0020.002ELAP estimate as of 06/20/2026
Platform feeUSD 16,5000.0142.2 %0.0100.010Contract as of 07/01/2026
ContingencyUSD 24,7930.0203.4 %0.0200.020ELAP estimate as of 06/20/2026
Financing costUSD 14,2110.0121.9 %0.0120.009ELAP estimate as of 06/20/2026
TaxesUSD 10,3470.0091.4 %0.0080.008ELAP estimate as of 06/20/2026
TotalUSD 736,0160.605100 %0.6070.613Contract 21 % · Quote 55 % · ELAP estimate 24 % as of 10/20/2026

Market reference: ELAP estimate ELAP · 2026 market reference, 19 budget prices · 09/15/2026. The platform average is that of the other 6 projects on this page. Each category is the sum of its lines in the bill of quantities.

03Open tenderanonymous until awarded, named afterwards

Structure · 2V fixed structure, 40 modules, drivenOpen · closes 10/31/2026 · 52 tables · 4 quotes
BidderOfferUnit priceTotalVersus lowestLead timeResult
Equipment · String inverter 100 kWOpen · closes 11/05/2026 · 10 pcs · 1 quote
BidderOfferUnit priceTotalVersus lowestLead timeResult

04Use of fundsUSD 0 disbursed of USD 596,074

SourcesUSD%
Land, in kindUSD 00.0 %
Equipment, in kindUSD 139,94219.0 %
CrowdUSD 550,00074.7 %
Bank debtUSD 46,0746.3 %
TotalUSD 736,016100 %
UsesUSD%
EquipmentUSD 182,94224.9 %
StructureUSD 109,56414.9 %
Electrical BOSUSD 112,23215.2 %
Medium voltageUSD 88,50012.0 %
Civil worksUSD 79,09210.7 %
Grid connectionUSD 47,5006.5 %
EngineeringUSD 14,6022.0 %
DevelopmentUSD 24,9443.4 %
TrusteeUSD 8,0001.1 %
InsuranceUSD 2,7890.4 %
Platform feeUSD 16,5002.2 %
ContingencyUSD 24,7933.4 %
Financing costUSD 14,2111.9 %
TaxesUSD 10,3471.4 %
TotalUSD 736,016100 %

In-kind contributions (USD 139,942: land and equipment for equity) do not go through the account. The rest is paid from the trust account against certified milestones by the independent engineer, and every disbursement is published here.

DateMilestoneAmountUseCertificateStatus
03/20/2027Financing closeUSD 64,046Engineering, development, trustee and placement feeon certificationPlanned
05/20/2027EPC signing and advanceUSD 79,804EPC advanceon certificationPlanned
06/20/2027Modules delivered to siteUSD 159,608Modules and inverters on deliveryon certificationPlanned
07/20/2027Pile drivingUSD 63,843Pile driving and structureon certificationPlanned
08/20/2027Mechanical installationUSD 69,164Mechanical installationon certificationPlanned
09/20/2027Electrical installationUSD 63,843Electrical BOS and cableson certificationPlanned
10/20/2027MV station and lineUSD 53,203MV stations, line and outgoing bayon certificationPlanned
11/20/2027CAMMESA commercial operationUSD 42,563EPC balance, contingency and retentionon certificationPlanned
Total through the trust accountUSD 596,074CAPEX minus in-kind contributions

05Who gets paid whatUSD 91,976 one-off · USD 26,688 per year

PartyWhoItemBasisAmount USDWhenSource
PlatformMercado SolarPlacement fee3 % of the crowd raise, once at closeUSD 16,500OnceContract Platform terms, art. 9 · 07/01/2026
PlatformMercado SolarAdministration and secondary market1 % of revenue, per yearUSD 1,287Per yearContract Platform terms, art. 10 · 07/01/2026
ELAPELAPEngineering0.012 USD/WpUSD 14,602OnceQuote EPC bid and trustee's proposal · 10/01/2026
ELAPELAPDevelopment0.018 USD/WpUSD 21,902OnceQuote EPC bid and trustee's proposal · 10/01/2026
TrusteeFiduciaria Pampa S.A. (example)Trust formationfixed feeUSD 8,000OnceQuote EPC bid and trustee's proposal · 10/01/2026
TrusteeFiduciaria Pampa S.A. (example)Trust administration0.8 % of revenue, per yearUSD 1,029Per yearQuote EPC bid and trustee's proposal · 10/01/2026
EPCInstalador Kaiken (example)EPC's declared margin10 % of the works in its scope (included in the bill of quantities)USD 27,469OnceQuote EPC bid and trustee's proposal · 10/01/2026
O&MInstalador Kaiken (example)Operation and maintenanceUSD 17,000 per MWp per yearUSD 20,686Per yearQuote EPC bid and trustee's proposal · 10/01/2026
BankBanco Regional (example)Debt structuring1 % of the debtUSD 461OnceQuote EPC bid and trustee's proposal · 10/01/2026
BankBanco Regional (example)Year-1 interest8 % a year on the debtUSD 3,686Per yearQuote EPC bid and trustee's proposal · 10/01/2026
Independent engineerEstudio Ingeniería Zonda (example)Technical review and construction certificationUSD 2,500 per MWpUSD 3,042OnceQuote EPC bid and trustee's proposal · 10/01/2026
One-off, within CAPEXUSD 91,97612.5 % of CAPEX
Annual, year 1USD 26,688from the payment waterfall
Declared conflict of interest. ELAP is at once engineer, developer and platform of this project: it charges for engineering, development and the platform fees. That is why the technical review is signed by an independent engineer (Estudio Ingeniería Zonda (example)), who also certifies every milestone before a disbursement.

06Production and assumptionsP50 2.25 GWh · P90 2.12 GWh per year · Source: ELAP estimate · ELAP · report rev B · P50/P90 study · 06/20/2026

Data or assumptionValue
P50 production2.25 GWh per year · 1,850 kWh/kWp
P90 production2.12 GWh per year · 1,740 kWh/kWp
Weather data sourcePVGIS-SARAH3
Years in the series2005 to 2023 (19 years)
Global horizontal irradiation (GHI)1,890 kWh/m² per year
Bifacial gainnot applicable (monofacial)
Total system losses13.8 %
Soiling2.0 % with quarterly cleaning
Availability99.0 %
Grid curtailment0.0 %
Annual module degradation0.4 % per year (manufacturer's linear warranty)
Combined uncertainty (1 σ)4.6 % · P90 = P50 × (1 − 1.28 σ)
Download ELAP's P50/P90 studyPDF of report rev B, with the weather series and the loss breakdown.

07RevenueDistributed generation · Law 27,424

ItemValueSource
PriceUSD 62/MWh: the meat-packing plant's avoided tariffContract Self-consumption contract · 07/15/2026
Term20 yearsContract Self-consumption contract · 07/15/2026
IndexationFollows the distribution company's tariffContract Self-consumption contract · 07/15/2026
CounterpartyMeat-packing plant, Villa DoloresContract Self-consumption contract · 07/15/2026
GuaranteesDirect debit and a 2-month depositContract Self-consumption contract · 07/15/2026
Energy covered78 % self-consumption; 22 % surplus to the distribution company at USD 40/MWhELAP estimate ELAP · report rev B · 06/20/2026
After the contractSame scheme until the end of the useful lifeELAP estimate ELAP · report rev B · 06/20/2026

08Payment waterfallyear 1 · projected

OrderItemBasisUSD year 1, P50% of revenueUSD year 1, P90Source
Energy sales revenue2.25 GWh · 78 % at USD 62/MWh and 22 % at USD 40/MWhUSD 128,672100.0 %USD 119,158Contract Self-consumption contract · 07/15/2026
1Operation and maintenanceUSD 17,000 per MWp per year−USD 20,68616.1 %−USD 20,686Quote EPC bid and trustee's proposal · 10/01/2026
2Operational all-risk insurance0.3 % of CAPEX per year−USD 2,2081.7 %−USD 2,208ELAP estimate ELAP · trust model, report rev B · 06/20/2026
3Trustee fee0.8 % of revenue−USD 1,0290.8 %−USD 953Quote EPC bid and trustee's proposal · 10/01/2026
4Platform administration fee1 % of revenue−USD 1,2871.0 %−USD 1,192Contract Platform terms, art. 10 · 07/01/2026
5Municipal fees and gross receipts tax1.2 % of revenue−USD 1,5441.2 %−USD 1,430ELAP estimate ELAP · trust model, report rev B · 06/20/2026
6Income tax35 % of profit, with 25-year depreciation−USD 24,07718.7 %−USD 20,847ELAP estimate ELAP · trust model, report rev B · 06/20/2026
7Debt service (principal and interest)USD 0.05 M at 8 % over 10 years−USD 6,8665.3 %−USD 6,866Quote EPC bid and trustee's proposal · 10/01/2026
8Inverter replacement reserveUSD 3,000 per MWp per year−USD 3,6502.8 %−USD 3,650ELAP estimate ELAP · trust model, report rev B · 06/20/2026
9Distribution to investors9.8 % of contributed capitalUSD 67,32452.3 %USD 61,326ELAP estimate ELAP · trust model, report rev B · 06/20/2026

First operation, taxes and debt; then reserves; and only after that the investors. The return on the sheet is the last line divided by the contributed capital (USD 689,942).

09Sensitivityyear 1 · same model as the payment waterfall · Source: ELAP estimate · ELAP · trust model, report rev B · 06/20/2026

CaseYear-1 returnVersus baseDistribution USDPer USD 1,000
Base case (P50)9.8 %—USD 67,324USD 98
Sale price −10 %8.6 %−1.2 ppUSD 59,211USD 86
P90 production8.9 %−0.9 ppUSD 61,326USD 89
CAPEX +10 %, with more debt8.6 %−1.2 ppUSD 59,303USD 86
20 % exchange-rate gap8.1 %−1.6 ppUSD 56,103USD 81

CAPEX +10 %: the overrun is financed with more debt. Exchange-rate gap: revenue is collected in pesos at the official rate and the investor converts to dollars at a rate 20 % higher.

10Construction progressplanned schedule · Source: ELAP estimate · ELAP · report rev B · schedule · 06/20/2026

MilestonePlannedActualDelay
EPC signing and advance04/15/2027pending—
Modules delivered to site06/15/2027pending—
Pile driving07/15/2027pending—
Mechanical installation08/15/2027pending—
Electrical installation09/15/2027pending—
MV station and line10/15/2027pending—
Energization11/15/2027pending—
CAMMESA commercial operation12/15/2027pending—
Main equipmentOf 7
Awarded or later1
Purchased0
Delivered to site0
Installed0
MonthPlannedActualCurve
04/20270 %—
05/202710 %—
06/202735 %—
07/202765 %—
08/202790 %—
09/2027100 %—

Purchase status of each item in section 1. Actual dates and progress: independent engineer's certificates.

11Change logpublic to everyone · Source: Contract · Contribution agreement no. 1 · 09/10/2026

DateWhat changedFromToWhy
09/10/2026Modules: price and sourceELAP estimate · USD 0.110/WpContract · USD 0.115/WpIn-kind contribution for equity by Importadora Andina (example).

When a figure changes source (estimated, quoted, contracted, actual), the previous one stays here.

12Documentsdata room

  • Trust agreementPending
  • ProspectusPDF · 10/2026View
  • Power purchase agreementPDF · 07/2026 · self-consumption contractRegistered users only
  • ELAP engineering report, rev BPDF · 06/2026View
  • Grid access studyPDF · 07/2026 · distribution company authorizationView
  • Independent engineer's technical auditPending
  • Quarterly financial statements of the trustPending